Yes. The City’s Official Plan and Zoning By-law apply to all development. Under the City's Zoning By-law, data centres are defined as “Information and Data Processing” use, which is permitted in the City’s employment zones.
All new employment area development, including expansions to existing buildings, are required to follow the Site Plan Control process. Site Plan does not deal with property use; rather, it focuses on how a property is developed. The Planning Act requires that Site Plan approval be delegated to City staff. Because the use is permitted by the Official Plan and Zoning By-law, the public and Council are not part of the review and approval process.
The Site Plan process ensures that the proposed building complies with the setback, height and size regulations of the Council-approved Zoning By-law, as well as parking and landscaping requirements. Staff also review the grading, driveway location and servicing infrastructure, including water, wastewater and stormwater management.
City staff also consult with Waterloo Region and Grandbridge Energy as part of the Site Plan review. Any comments, concerns or conditions of approval from these agencies are included in the conditions of Site Plan approval.
A building permit is mandatory for new constructions or alterations to an existing building and must comply with the Zoning By-law. A building permit must be issued once the applicant demonstrates that all requirements of the Ontario Building Code have been met.