Current Projects

For a list of road closures around Cambridge, visit our road closures page. For any emergencies and/or urgent requests within the project boundary, please contact Infrastructure and Development at (519) 621-0740. If you have any questions or concerns regarding any of the projects listed below, please email the Project Management Office at servicecambridge@cambridge.ca.

City of Cambridge Active Transportation Capital Projects Status
Name Status %Completed Schedule Budget Project Manager
Active Transportation (2023) - Trail Con Project work complete 100% Nov-23 to Sep-25 $148,600 Jason Leach
AT Design - Dan Spring Way Trail Delayed 3% Jan-27 to Dec-27 $100,000 Jason Leach
Avenue Rd MUT (Gail St to Franklin Blvd) Approved 0% Jan-26 to Dec-26 $83,200 Jason Leach
Fisher Mills Rd MUT (Hespeler to 355) Approved 0% Jan-26 to Dec-26 $110,000 Jason Leach
Fisher Mills Rd MUT (Hespeler to Scott) Approved 0% Jan-26 to Dec-26 $52,500 Jason Leach
Hespeler Pedestrian Bridge Design In progress 7% Jan-27 to Dec-27 $521,200 Jason Leach
Hespeler Trail Project - Queen to Guelph Project work complete 80% Mar-21 to Dec-25 $183,849 Jason Leach
Multi-Use Trail - Dunbar Rd Phase 3 In progress 50% Dec-24 to Jun-26 $98,653 Deepak Manoj
Trail Bridge Design 2 Delayed 4% Feb-25 to Dec-26 $147,400 Jason Leach
Trail Dev - Pinebush/Branthaven In progress 90% Jan-22 to Nov-26 $247,500 Sarah Austin
Trail Renewal - Northview Heights Trail Delayed 4% Feb-25 to Nov-27 $498,200 Jason Leach

City of Cambridge Community Improvement Capital Projects Status
Name Status %Completed Schedule Budget Project Manager
Cemeteries Master Plan Project work complete 100% Sep-23 to Nov-25 $131,779 Michael Hausser
City-Wide Speed Limit Sign Implement In progress 75% Mar-24 to Nov-26 $288,256 Jason Leach
City-Wide Speed Limit Signage (2025) In progress 75% Dec-24 to Nov-26 $182,098 Jason Leach
Mountview & New Hope Columbarium Design In progress 15% Dec-24 to Oct-26 $90,000 Nathan Zrini
Old Mill Rd Traffic Calming In progress 70% Jan-22 to May-26 $168,000 Jason Leach
Placemaking Study and Pilot Project In progress 22% Mar-23 to Sep-26 $150,000 Alix Aitken
Public Art 50th Anniversary Project work complete 100% Mar-23 to Dec-25 $290,000 Shane Taylor
Sidewalk Installation - Edward Street (2 Delayed 4% Jul-24 to May-26 $75,000 Jason Leach

City of Cambridge Community Planning Capital Projects Status
Name Status %Completed Schedule Budget Project Manager
Active Transportation Feasibility Review Approved 0% May-26 to Dec-26 $110,000 Jason Leach
Analysis City Owned Real Estate Assets Delayed 0% Mar-26 to Dec-26 $100,000 Michael Launslager
Assessing Infilling & Intensification Project work complete 100% Apr-15 to Dec-24 $467,580 John Matthew Blevins
Asset Management Plan - Phase 3 Project work complete 98% Nov-23 to Jan-26 $357,000 Johannes Krijnen
BIA Modernization In progress 75% Nov-24 to Mar-26 $100,000 Michael Launslager
Consulting Services - Planning Project work complete 99% Mar-21 to Dec-25 $97,486 Brandon Kent Demeester
Development Charges Update (2022) In progress 80% Jul-22 to Feb-26 $175,642 Katherine Hyde
Galt Connected - Mobility and Streets Approved 0% Jan-26 to Dec-26 $400,000 Jason Leach
Galt Core Heritage Conservation District In progress 80% Oct-20 to Jun-26 $161,078 Laura Waldie
Galt Special Policy Area Review Approved 0% Sep-26 to Jul-28 $275,000 Melissa Castellan Aldunate
HAF Additional Res Unit Assistance Prog. Project work complete 95% Mar-24 to Dec-26 $1,563,400 Laura Dewar
HAF Affordable Housing CIP In progress 90% Mar-24 to Mar-26 $845,000 John Matthew Blevins
HAF Delegation of Authority Enhancements Project work complete 100% Mar-24 to Dec-25 $281,400 Laura Dewar
HAF Form Based Zoning By-Law In progress 90% Jun-24 to Feb-26 $570,800 Bryan Cooper
HAF Housing Needs Assessment & Strategy Project work complete 100% Mar-23 to Jan-26 $420,100 John Matthew Blevins
HAF Strategic Growth Area Secondary Plan In progress 75% Mar-24 to Dec-26 $366,500 John Matthew Blevins
HAFMunicipal Land for Affordable Housing In progress 85% Jun-24 to Dec-26 $5,038,735 John Matthew Blevins
Heritage Conserv District Study Hespeler In progress 95% Mar-23 to Sep-26 $100,000 Jeremy Edward Daniel Parsons
Heritage Property Designations (OHA) In progress 76% Mar-24 to Dec-26 $403,800 Nick R Borcescu
Heritage Register Review In progress 40% Mar-24 to Jan-26 $250,000 Nick R Borcescu
Hespeler Transportation Assessment In progress 3% Mar-24 to Jul-26 $150,000 Jason Leach
Inclusionary Zoning In progress 75% Jan-23 to Mar-27 $125,000 John Matthew Blevins
Library Facilities Master Plan In progress 15% Dec-24 to Mar-26 $90,000 Mirna Raponi
Northwest Hespeler Secondary Plan & MESP Approved 0% Mar-26 to Apr-27 $1,500,000 Sarah Austin
Official Plan Review In progress 0% Jan-26 to Dec-28 $325,000 Bryan Cooper
Older Adult Strategy In progress 81% Jan-22 to Apr-26 $76,000 Alix Aitken
Operations Facility Master Plan In progress 60% Apr-22 to Mar-26 $250,000 Michael Hausser
Preston Secondary Plan In progress 45% Dec-24 to Sep-26 $350,000 John Matthew Blevins
Rec Facility Sponsorship & Naming Plan In progress 55% May-22 to Dec-26 $150,000 Shane Taylor
Recreation Facilities Action Plan - Ph 1 Delayed 0% Dec-24 to Jun-26 $100,000 Meghan Hunter
Recreation Services Rates & Fees Review In progress 5% Sep-24 to Dec-26 $75,000 Nicole Cichello
Residential Parking Bylaw Review In progress 7% Mar-21 to Jul-26 $80,000 Christine Kinahan
River Road Area - Class EA In progress 45% Mar-23 to Jun-26 $200,000 Sarah Austin
Road Safety Audits In progress 5% Dec-24 to Sep-26 $120,000 Christine Kinahan
Road Safety Review & Action Plan (2025) In progress 2% Dec-24 to Jul-27 $200,000 Christine Kinahan
Saginaw Parkway at Green Vista Drive Int In progress 7% Jun-26 $100,000 Jason Leach
Sanitary Sewer Model Update (2022) In progress 95% Jan-22 to Apr-26 $250,000 Sarah Austin
Stormwater Technical Study Delayed 1% Mar-22 to Mar-27 $275,000 Sarah Austin
Strategic Plan Approved 0% Jan-26 to Dec-28 $165,600 Jenna Brown-Jowett
SWM Funding Study - Implementation Plan In progress 90% Jul-22 to Feb-26 $200,000 Sheena Pawliwec

City of Cambridge Condition Assessment Capital Projects Status
Name Status %Completed Schedule Budget Project Manager
Heritage Condition Assessment – Phase 2 In progress 90% Mar-23 to Jan-26 $242,100 Ellise Paltser
SWM Pond Condition Assessments In progress 65% Dec-24 to Feb-29 $123,000 Andrew Schenk

City of Cambridge Design
Name Status %Completed Schedule Budget Project Manager
Corydon Pump Station Upgrade – Design In progress 50% Jan-23 to Jun-26 $100,000 Scott Murray Macdonald

City of Cambridge Environmental Stewardship Projects Status
Name Status %Completed Schedule Budget Project Manager
Energy Mgmt - Corporate Buildings In progress 40% Dec-24 to Mar-27 $150,000 Ryan Hoeksma
GHG Reduction Feasibility Study Project work complete 99% Jan-22 to Feb-26 $299,494 Ryan Hoeksma
Region - 188 Water St In progress 5% Dec-24 to Jan-28 $110,000 Sarah Austin
SWM Pond Fence Repairs In progress 80% Nov-25 to Jan-26 $100,000 Prasad Samarakoon

City of Cambridge Equipment Purchase Projects Status
Name Status %Completed Schedule Budget Project Manager
Bunker Gear (New Personnel) Year 1 Approved 0% Sep-26 to Dec-26 $100,000 Brad Michael Churchill
Bunker Gear Phase 2 In progress 95% Dec-24 to Feb-26 $264,000 Brad Michael Churchill
Equipment Growth Approved 0% Feb-26 to Feb-29 $529,200 Garth Buttenham
Equipment Growth (2024) In progress 61% Mar-24 to Dec-26 $326,600 Garth Buttenham
Equipment Growth (2025) In progress 31% Dec-24 to Dec-26 $816,500 Garth Buttenham
Equipment Replacement Approved 0% Feb-26 to Feb-29 $4,190,000 Garth Buttenham
Equipment Replacement (2023) In progress 91% Mar-23 to Jan-26 $2,954,478 Michael Hewlett
Equipment Replacement (2024) In progress 96% Jan-24 to Mar-26 $4,170,000 Garth Buttenham
Equipment Replacement (2025) In progress 41% Dec-24 to Dec-26 $4,111,000 Garth Buttenham
Fire Fighting Equipment Phase 1 In progress 95% Dec-24 to Feb-26 $64,900 Brad Michael Churchill
Fire Fighting Equipment Phase 2 Approved 0% Jan-26 to Dec-26 $71,400 Brad Michael Churchill
Fire Fleet Apparatus (2024) - Pumper In progress 40% Feb-23 to Jul-26 $1,322,900 Brad Michael Churchill
Fire Fleet Apparatus (2025) - Rescue In progress 20% Dec-23 to Jul-27 $1,579,845 Brad Michael Churchill
Fire Fleet Apparatus (2029) In progress 20% Nov-29 $2,392,000 Brad Michael Churchill
Fire Fleet Growth (2025) In progress 40% Jan-25 to May-29 $1,535,311 Brad Michael Churchill
Fleet Hoist Replacement Approved 0% Feb-26 to Feb-27 $101,800 Garth Buttenham
Laptop/Desktop Replacement Lifecycle Approved 0% Jan-26 to Dec-26 $286,000 Harshvardhansinh J Mahida
Library Computer Equipment Approved 0% Jan-26 to Dec-26 $75,500 Mirna Raponi
Library Computer Equipment (2024) In progress 60% Jan-24 to Jan-26 $453,000 Mirna Raponi
Library Materials Approved 0% Jan-26 to Sep-26 $109,000 Mirna Raponi
Library Materials (2025) Project work complete 100% Dec-24 to Oct-25 $109,000 Mirna Raponi
Light Fire Fleet Approved 0% Jan-26 to Dec-26 $166,400 Brad Michael Churchill
Public Safety Equipment Phase 1 In progress 90% Dec-24 to Mar-26 $76,000 Damond Jamieson
Public Safety Equipment Phase 2 Approved 0% Jan-26 to Dec-26 $64,500 Damond Jamieson

City of Cambridge Facility Renovation Projects Status
Name Status %Completed Schedule Budget Project Manager
1300 Bishop - Washrooms/HVAC Approved 0% Jan-26 to Dec-26 $254,300 Ryan Hoeksma
19 Cambridge Renovation In progress 11% Dec-24 to Dec-26 $202,000 Steven Ruffini
Allan Reuter - Exterior Steps/Guardrail Approved 0% Mar-26 to Dec-26 $73,700 Slobodanka Lekic
Arena Elevator Replacements In progress 75% Sep-24 to Mar-27 $1,500,000 Ryan Hoeksma
Arena Safety Netting Delayed 0% Dec-24 to Dec-26 $175,000 Olu Ojikutu
BOC - Concrete Floor Drainage Upgrades Approved 0% Jan-26 to Jun-27 $1,234,400 Steven Ruffini
Boiler Replacement (Old Post Office) Approved 0% Jan-26 to Sep-26 $60,000 Mirna Raponi
City Hall - Elevator Accessibility Approved 0% Jan-26 to Dec-26 $101,800 Meghan Hunter
City Hall Campus Revitalization Phase 1 In progress 0% Jan-26 to Dec-26 $300,000 Nathan Zrini
Corporate Facilities - Design Approved 0% Feb-26 to Jun-27 $305,300 Slobodanka Lekic
Dickson Arena - Ice Equipment Repairs Approved 0% - $164,000 Olu Ojikutu
Duncan McIntosh Arena - Sitework Approved 0% Jan-26 to Dec-26 $50,000 Juan David Henao Lopez
Energy Management - Corporate Buildings Approved 0% Jan-26 to Dec-26 $1,413,400 Ryan Hoeksma
Entrance Accessibility (Old Post Office) Approved 0% Jan-26 to Jul-26 $101,000 Mirna Raponi
Ferguson Homestead Heritage Restoration In progress 9% Dec-24 to Dec-26 $244,000 Juan David Henao Lopez
Fire Station 1 Kitchen In progress 0% Dec-24 to Jun-26 $135,000 Steven Ruffini
Fire Station 1 Lunchroom and Lounge Approved 0% Jan-26 to Dec-26 $162,800 Steven Ruffini
Fire Station 1 Washroom Approved 0% Jan-26 to Dec-26 $234,700 Ryan Hoeksma
Fire Station 4 Expansion Design In progress 1% Dec-24 to Jun-27 $228,800 Steven Ruffini
Fire Station 5 Sewer Pipe In progress 21% Dec-22 to Dec-26 $120,000 Juan David Henao Lopez
Fire Station 5 Windows and Doors Approved 0% Jan-26 to Dec-26 $153,200 Steven Ruffini
Galt Arena Roof Window Replacement In progress 12% Dec-24 to Jun-26 $273,700 Slobodanka Lekic
Glass Railing Replacement (Hespeler) Approved 0% Jan-26 to Dec-26 $202,000 Mirna Raponi
Heritage Reno - Exterior Market Building In progress 12% Nov-25 to Mar-27 $848,400 Juan David Henao Lopez
Heritage Reno – H. Town Ctr & F. Market In progress 60% May-24 to Dec-26 $300,000 Juan David Henao Lopez
Hespeler Arena Dehumidifiers In progress 90% Mar-23 to Jan-26 $1,045,400 Ryan Hoeksma
Johnson Ctr - Skylight, Window & Lights In progress 6% Dec-24 to Jun-26 $287,900 Steven Ruffini
Library - Bldg Envelope Repair (Preston) Project work complete 100% Jan-22 to Jun-24 $367,800 Mirna Raponi
Library Atria Revit. (Queen's Square) In progress 15% Dec-24 to Sep-26 $252,500 Mirna Raponi
Library Elevator Modernization Hespeler In progress 10% Dec-24 to Jun-26 $176,800 Mirna Raponi
Library HVAC Replace (Queen's Square) In progress 10% Jan-24 to Jan-26 $86,000 Mirna Raponi
Library HVAC Replacement (Preston) In progress 5% Jan-24 to Jan-26 $245,000 Mirna Raponi
Library HVAC Replacement Queen Square Approved 0% Jan-26 to May-26 $277,800 Mirna Raponi
Library Queens Sq Entrance Renovations In progress 5% Dec-21 to Jan-26 $120,000 Mirna Raponi
Library Roof Replace - Preston In progress 5% Nov-23 to Jan-26 $696,900 Mirna Raponi
Library Roof Replace - Queen Square (92) In progress 5% Jul-24 to Jan-26 $418,000 Mirna Raponi
Lutz House Heritage Restoration In progress 17% Dec-24 to Jun-26 $152,000 Juan David Henao Lopez
Mountview Maintenance - Roof Replace Approved 0% Jan-26 to Dec-26 $65,100 Slobodanka Lekic
Newland Pool Accessibility Improvements Project work complete 99% Dec-22 to Feb-26 $183,981 Ryan Hoeksma
Parklawn Cemetary Roof Replacement In progress 95% Dec-24 to Jan-26 $84,400 Ryan Hoeksma
Preston Auditorium - Design Project work complete 95% Jan-20 to Dec-25 $1,954,474 Shane Taylor
Preston Scout House Heritage Restore In progress 35% Dec-24 to Jun-26 $20,448 Juan David Henao Lopez
Riverside Water Building Roof Replace In progress 90% Dec-24 to Jun-26 $267,800 Ryan Hoeksma
Roof Replace - Durward Centre Approved 0% Jan-26 to Dec-26 $525,200 Steven Ruffini
WG Johnson - Family Washroom Renovation Approved 0% Jan-26 to Dec-26 $295,000 Slobodanka Lekic
WG Johnson Pool Amenity Approved 0% Jan-26 to Dec-26 $156,000 Meghan Hunter

City of Cambridge Land/Property Acquisition Projects Status
Name Status %Completed Schedule Budget Project Manager
Land Acquisition 1 - Confidential Delayed 90% Mar-19 to Mar-26 $3,975,000 Neil Lacey
Utility Easement Acquisition (2023) In progress 80% Mar-23 to Jan-26 $150,000 Neil Lacey

City of Cambridge Networks & Information Mgmnt Projects Status
Name Status %Completed Schedule Budget Project Manager
Network Eq. Lifecycle/Replace 2024 In progress 60% Mar-24 to Dec-26 $400,000 Hristo Nikolov

City of Cambridge New Enterprise Application Projects Status
Name Status %Completed Schedule Budget Project Manager
HAF Development Guide & Portals Project work complete 100% Jun-24 to Jan-25 $364,600 Tanya Gies
HAF Digital Twin Accelerated Approvals In progress 27% Jun-24 to Sep-26 $3,896,400 Kirby Childerhose

City of Cambridge New Facility Projects Status
Name Status %Completed Schedule Budget Project Manager
Accessible Ball Diamond - Design In progress 85% Mar-24 to Dec-26 $150,000 Nathan Zrini
Recreation Complex - Construction In progress 30% Mar-24 to Dec-27 $105,536,600 Shane Taylor
Recreation Complex - Design In progress 90% Jan-20 to Dec-26 $6,437,020 Shane Taylor

City of Cambridge Park Development Projects Status
Name Status %Completed Schedule Budget Project Manager
Accessible Ball Diamond - Construction In progress 15% Dec-24 to Feb-27 $3,025,000 Nathan Zrini
Cam West Bismark Park South Delayed 0% Feb-26 to Sep-27 $390,000 Vicki Armitage
Cambridge Dog Park Design Delayed 0% Jan-27 to Dec-27 $100,000 Nathan Zrini
Cricket Feasibility Study In progress 25% Mar-24 to Mar-26 $41,315 Michael Hausser
Fountain Soccer Netting In progress 1% Apr-26 to Dec-26 $231,100 John Paul Bartle
Hespeler Skate Park Design In progress 5% Dec-24 to Dec-27 $110,000 Nathan Zrini
Jumpstart Accessible Sports Amenity Cons In progress 85% Oct-24 to Jun-27 $961,641 Vicki Armitage
Land Acquisition - Confidential 3 In progress 0% Dec-24 to Oct-26 $4,255,000 Neil Lacey
Lions Can Amera Splashpad Design/Build In progress 50% Feb-24 to Sep-26 $860,000 Nathan Zrini
Park Dev - Treasure Hill Delayed 0% Apr-27 to Oct-28 $677,800 Vicki Armitage
Park Dev - Wesley Blvd Community Park In progress 3% Feb-26 to Nov-26 $1,248,000 Shane Taylor
Park Dev Isherwood Design Delayed 2% Jan-26 to Sep-27 $51,000 Vicki Armitage
Park Dev Lakeview/Morrison Design Delayed 2% Feb-26 to Oct-27 $71,700 Vicki Armitage
Park Dev Saginaw Subdivision Delayed 2% Jul-24 to Nov-26 $235,000 Vicki Armitage
Soper Park Outdoor Pool Design and Plan In progress 75% Mar-24 to Dec-28 $425,000 Steven Ruffini
Soper Park Plan In progress 5% Dec-25 to Dec-26 $25,000 Nathan Zrini
Trail Dev - Cambridge West In progress 96% Sep-23 to Sep-26 $679,400 Vicki Armitage
Trail Dev - South Point Ph 2 (Bosdale) In progress 5% Apr-26 to Oct-27 $356,700 Vicki Armitage
Trail Dev - Treasure Hill In progress 75% Dec-24 to May-28 $634,000 Vicki Armitage

City of Cambridge Park Renewal Projects Status
Name Status %Completed Schedule Budget Project Manager
Basketball Refurb - Churchill & Weaver In progress 15% Dec-24 to Feb-27 $400,000 Nathan Zrini
Churchill & Birkinshaw Path Lighting In progress 5% Dec-24 to Jun-26 $90,000 Nathan Zrini
Churchill Picnic Pavillion/Pond Design In progress 0% Dec-24 to Dec-26 $119,000 Nathan Zrini
Playground Replace - Hespeler Optimist Approved 0% Jan-26 to Oct-26 $528,600 Nathan Zrini
Playground Replacement - Forbes Park Approved 0% Apr-26 to Aug-26 $669,100 Nathan Zrini
Playground Replacement - Hill 60 Park Approved 0% Mar-26 to Nov-26 $210,100 Nathan Zrini
Playground Replacement - Willard Park Approved 0% Apr-26 to Jul-26 $630,200 Nathan Zrini
Riverside Park Heritage Gates Design Approved 0% Mar-26 to Dec-26 $62,400 Nathan Zrini

City of Cambridge Reconstruction Projects Status
Name Status %Completed Schedule Budget Project Manager
Black Bridge Road and Bridge, Design In progress 99% May-18 to Jun-26 $1,660,669 Scott Murray Macdonald
Blackbridge and Townline Road Utility Project work complete 99% Mar-23 to Feb-26 $331,000 Scott Murray Macdonald
Blair Road Retaining Wall Construction In progress 0% Jan-26 to Dec-26 $1,800,000 Matt Holland
Cooper Street Reconstruction In progress 0% Jan-26 to Dec-27 $3,890,000 Matt Holland
Cooper Street Reconstruction (2025) In progress 40% Dec-24 to Jan-28 $4,494,894 Matt Holland
Dayton St. Reconstruction In progress 0% Jan-26 to Nov-27 $1,964,000 Scott Murray Macdonald
Elgin St N (Glamis to CP Rail) Phase 1 In progress 0% Jan-26 to Dec-27 $12,515,000 Jamie Croft
Glendale Place and Ash St Reconstruction Project work complete 100% Mar-24 to Dec-25 $1,082,593 Scott Murray Macdonald
Henry, Serviss and McAuslin St Recon In progress 1% Jan-26 to Dec-28 $4,305,000 Deepak Manoj
Infrastructure Design In progress 0% Jan-26 to Dec-27 $1,000,000 Jamie Croft
Infrastructure Design (2023) In progress 60% Jan-23 to Jun-26 $521,000 Jamie Croft
Infrastructure Design (2025) In progress 20% Jan-25 to Dec-27 $820,000 Jamie Croft
Keffer St. and Laneway 13 Rehabilitation In progress 8% Jan-26 to Dec-26 $1,000,000 Kyle Novak
Moore St and Hamilton St Reconstruction In progress 0% Apr-26 to Dec-27 $3,700,000 Andrew Schenk
Queen Street West Reconstruction In progress 1% Dec-24 to Jan-28 $3,200,000 Matt Holland
Ramore St and Gilholm Ave Reconstruction In progress 12% Apr-26 to Dec-27 $2,284,000 Kyle Novak
Region - Water St (Ainslie to Simcoe St) Delayed 10% Jan-22 to Nov-26 $780,000 Sarah Austin
Riverside Dam Detailed Design In progress 98% Mar-23 to Jun-26 $525,000 Scott Murray Macdonald
Saginaw at Green Vista Dr Intersection Approved 0% Apr-26 to Dec-27 $884,000 Jason Leach
Townline Road Reconstruction In progress 0% Jan-26 to Nov-28 $12,064,000 Scott Murray Macdonald
Watermain Decom Design Along Grand River Project work complete 99% Feb-23 to Feb-26 $155,962 Scott Murray Macdonald

City of Cambridge Renewal Projects Status
Name Status %Completed Schedule Budget Project Manager
Asphalt Resurfacing Program In progress 0% Feb-26 to Dec-26 $1,600,000 Brandon Kent Demeester
Blackbridge Rd and Bridge Reconstruction In progress 17% May-24 to Dec-26 $20,600,000 Scott Murray Macdonald
Bridge & Culvert Design In progress 70% Mar-24 to Sep-26 $250,000 Jamie Croft
Bulk Fill Station Replacement Approved 0% May-26 to Aug-26 $100,000 Jessie L Koczynasz
Burnett Sanitary Sewer and Manhole Recon In progress 5% Jul-26 to Jul-27 $150,000 Kyle Novak
Duncan McIntosh Arena - Ice Equipment Approved 0% - $407,000 Olu Ojikutu
Elgin Street North Utility Relocations In progress 20% Mar-24 to Aug-26 $300,000 Jamie Croft
Entry Sign Replacement Approved 0% Jan-26 to Jun-27 $50,000 Alana Russell
Fire Station 1 - Training Tower Tiles Approved 0% Jan-26 to Dec-26 $122,100 Steven Ruffini
Hespeler Arena - Pumping Equipment Approved 0% Apr-26 to Dec-26 $54,000 Ryan Hoeksma
Infrastructure Design (2024) In progress 70% Sep-24 to Dec-26 $536,000 Jamie Croft
Jacobs Landing Flood Wall Repair In progress 1% Jul-26 to Jul-27 $150,000 Kyle Novak
Laneway Renewal Program In progress 5% May-26 to Dec-26 $1,465,000 Andrew Schenk
Newland Pool Walkway Improvements In progress 25% - $175,000 Andrew Schenk
Parking Lot - Westminster & Water St N Delayed 0% Jan-26 to Dec-26 $53,000 Jason Leach
Pedestrian Bridges Deck Replacements In progress 50% Mar-23 to Dec-26 $216,000 John Paul Bartle
Riverside Artesian Well Outlet Changes In progress 33% Dec-24 to Jul-27 $68,000 Andrew Schenk
Riverside Dam Repair In progress 65% Dec-24 to Dec-26 $425,000 Scott Murray Macdonald
Riverside Dam Safety Improvements In progress 0% Mar-26 to Nov-27 $200,000 Scott Murray Macdonald
SCADA System Review Approved 0% Jan-26 to Dec-26 $100,000 Jason Alexander
Sewer Lining Citywide In progress 2% Jan-26 to Dec-26 $2,400,000 Kyle Novak
Siphon Operation Procedures Approved 0% Jan-26 to Jun-27 $100,000 Robert James Black
Snow Storage Facility Design & Permits In progress 0% May-26 to Dec-27 $171,600 Jamie Croft
Storm Pond Design In progress 0% Jan-26 to Dec-26 $140,000 Andrew Schenk
W River Rd Trunk Sanitary Access- Design In progress 61% Apr-24 to Jun-26 $90,000 Scott Murray Macdonald
Water Meter Replacement Program Approved 2% Jan-26 to Dec-26 $1,032,300 Harpreet Singh Sumra
Watermain Decomm. Along Grand River In progress 0% Jul-26 to Oct-27 $1,100,000 Scott Murray Macdonald
Watermain Lining Citywide Approved 1% Jan-26 to Dec-27 $4,950,000 Deepak Manoj
Watermain Lining Rehabilitation Design In progress 85% Dec-24 to Jul-27 $172,728 Deepak Manoj
WG Johnson - Building Automation Systems Approved 0% Jan-26 to Dec-26 $123,300 Ryan Hoeksma
Witmer Pumping Station - Construction Approved 0% Feb-26 to Dec-28 $1,560,000 Robert James Black
Witmer Pumping Station Upgrade- Design In progress 10% Dec-24 to Sep-27 $291,909 Robert James Black

City of Cambridge Security & Risk Mgmnt Projects Status
Name Status %Completed Schedule Budget Project Manager
Cloud Strategy Implementation - Phase 2 Approved 0% Jan-26 to Dec-26 $200,000 Hristo Nikolov
Migration of Integrations to Cloud Approved 0% Jan-26 to Dec-26 $500,000 Wei Li Wang

City of Cambridge Strategy & Governance Projects Status
Name Status %Completed Schedule Budget Project Manager
Communitech Partnership Delayed 11% Dec-24 to Dec-26 $50,000 Karisa Downey
Records and Information Management Project work complete 100% Mar-24 to Dec-25 $130,253 Veronica Mary Carr

City of Cambridge Technology Upgrades Projects Status
Name Status %Completed Schedule Budget Project Manager
ActiveNet Roadmap Implementation (2024) In progress 20% Feb-25 to Dec-26 $150,000 Ahmed Kassad
ActiveNet Roadmap Implementation 2019 Project work complete 100% Mar-19 to Feb-26 $75,000 Ahmed Kassad
Amanda Roadmap Implementation In progress 95% Jan-22 to Jan-26 $450,000 Dianne Clare Glofcheskie
Amanda Roadmap Implementation (2023) In progress 20% Jan-23 to Sep-26 $250,000 Dianne Clare Glofcheskie
Amanda Roadmap Implementation (2024) Delayed 0% Mar-26 to Dec-27 $300,000 Dianne Clare Glofcheskie
BI/Business Data Warehouse Assessment Approved 0% Jan-26 to Dec-26 $100,000 Nikhilkumar Patel
BI/BW Strategy Development & Enhancement In progress 95% Jan-22 to Feb-26 $100,000 Nikhilkumar Patel
Camera and Security In progress 55% Jun-25 to Jun-26 $150,000 Rutvik Shah
cityONE (SAP) Enhancements Approved 0% Jan-26 to Dec-26 $208,000 Samir Desai
cityONE (SAP) Lifecycle Updates Approved 0% Jan-26 to Dec-26 $208,000 Samir Desai
cityONE (SAP) Lifecycle Updates (2025) In progress 35% Dec-24 to Jun-26 $200,000 Samir Desai
cityONE Lifecycle Enhancements (2025) In progress 10% Dec-24 to Jun-26 $200,000 Samir Desai
cityONE Lifecycle Updates & Replace 2024 Project work complete 99% Jan-24 to Jan-26 $500,000 Samir Desai
Cloud Strategy and Implementation In progress 15% Dec-24 to Dec-26 $100,000 Ryan Small
Connected City (2024) In progress 35% Mar-24 to Dec-26 $150,000 Syed Murtaza
Corporate Payment Sys Implementation Delayed 0% Jan-27 to Dec-27 $300,000 Revathi Devendran
Corporate Payment System Assess/Upgrade In progress 95% Mar-19 to Jan-26 $75,000 Revathi Devendran
Corporate Payment System Lifecycle In progress 10% Mar-25 to Dec-26 $400,000 Revathi Devendran
Customer Relationship Management In progress 25% Jan-23 to Dec-26 $228,884 Mohammad Mamun
Customer Relationship Mgmt Software Delayed 0% Aug-25 to Dec-26 $400,000 Mohammad Mamun
Database Middleware Integration/Process In progress 55% Jun-22 to Apr-26 $100,000 Ryan Small
Digital Transform Citizen Portal Enhance In progress 50% Sep-21 to Jun-26 $250,000 Helly Jayesh Shah
Disaster Recovery Site Enhancements In progress 5% Sep-25 to Jun-26 $300,000 Ryan Small
Fire Record Mgmt System Implementation In progress 5% Jan-26 to Dec-26 $250,000 Kirby Childerhose
GIS Roadmap Implementation (2024) In progress 20% Mar-24 to Dec-26 $350,000 Nicole Walker
GIS Roadmap Implementation (2025) Delayed 5% Jan-26 to Dec-26 $100,000 Nicole Walker
Integration of Systems and Database In progress 15% Dec-24 to Dec-26 $250,000 Ryan Small
Laptop/Desktop Replacements (2025) Project work complete 100% Dec-24 to Oct-25 $250,000 Harshvardhansinh J Mahida
Library Computer Equipment (2025) In progress 20% Dec-24 to Jan-26 $271,200 Mirna Raponi
Parking Digitization and Service Enhance Approved 0% Jan-26 to Dec-26 $78,000 Syed Murtaza
Parking System & Process Digitization 24 In progress 45% Apr-25 to May-26 $100,000 Syed Murtaza
Renewal Capital Planning Support Tool In progress 47% Mar-23 to Dec-26 $250,000 Johannes Krijnen
Security Camera Hardware & App 2024 Project work complete 100% Mar-24 to Jan-26 $75,000 Rutvik Shah
SharePoint Roadmap Implementation Approved 0% Jan-26 to Dec-26 $70,600 Helly Jayesh Shah
SharePoint Roadmap Implementation (2024) In progress 90% May-25 to Mar-26 $100,000 Helly Jayesh Shah
Telephone Modernization - Teams 2024 In progress 95% Mar-24 to Feb-26 $300,000 Darren Hutchings
Website Renewal In progress 60% Dec-24 to Feb-26 $250,000 Alana Russell
Work Order Management System Enhance Approved 0% Jan-26 to Dec-26 $500,000 Jennifer Wrzala
Work Order Mgmt System Enhance 2024 In progress 35% Mar-24 to Jun-26 $350,000 Jennifer Wrzala

Current projects map

View map in full screen