Stay up-to-date on City of Cambridge Road Construction projects.  To learn about current Regional projects, visit the Region of Waterloo's website

Bruce Street and Spruce Street

Overview

The reconstruction project will include work on Bruce Street (from Harris Street to Main Street) and Spruce Street (from Bruce Street to Main Street). The project includes replacement of watermains, sanitary sewers, and storm sewers. It will also include reconstruction of the asphalt, road base and sub-base, concrete sidewalks, and concrete curb and gutter.

Timeline

Planned construction start date: April 21, 2025

Progress

  • Bruce Street construction work is 0% complete.
  • Spruce Street construction work is 0% complete.

Road Closures

  • N/A

Notices

Contact Information

 

Steven Huang
Project Engineer
City of Cambridge
(519) 623-1340 ext. 4616

Byng Ave, Kay St, and Richardson St

Overview

The reconstruction project will include work on Richardson Street (from Cedar Street to Victoria Avenue), Kay Street (from Cedar Street to Victoria Avenue) and Byng Avenue (from Salisbury Street to the end of the road). The project includes replacement of watermains, sanitary sewers, and storm sewers. It will also include reconstruction of the asphalt, road base and sub-base, concrete sidewalks, and concrete curb and gutter.

Timeline

Planned construction start date: April 15, 2025

Progress

  • Richardson Street - Construction work is 0% complete.
  • Kay Street - Construction work is 0% complete.
  • Byng Avenue - Construction work 0% complete.

Road Closures

  • N/A

Notices

Contact Information

Steven Huckabone
Project Manager
City of Cambridge
(519) 623-1340 ext. 4304   

Cooper Street Reconstruction

Overview

The Cooper Street reconstruction project will include work on Cooper St (from Queen St E to Phin Ave), Queen St E (from Chapel St to Cooper St), and Chapel St (from Queen St E to end). The project generally includes the construction of approximately 1,000m of 200mm diameter watermain, 1,250m of 300mm to 975mm diameter storm sewer, 1,000m of 200mm and 250mm diameter sanitary sewer, 9,800m2 of asphalt roadway, 2,500m2 of concrete sidewalk, 2,000m of concrete curb and gutter and other miscellaneous works.

Timeline

The planned construction start date is on or about May 5, 2025. The project will be completed over two stages, with one stage per year.

Progress

  • Stage 1: Chapel Street construction work is 5% complete and currently underway.
  • Stage 1: Queen Street E construction work is 0% complete.
  • Stage 1: Cooper Street from Queen St E to McMaster St construction work is 0% complete.
  • Stage 2: Cooper Street from Queen St to McMaster St construction work is 0% complete. This work will begin in 2026.

Road Closures

  • Stages will be closed as required for construction works. The roadway will still be available for local traffic only.
  • During the deep storm works located on Cooper St between Queen St E and Kribs St, the roadway will be completely closed.

Notices

Contact Information

Matt Holland
Project Engineer
City of Cambridge
(519) 623-1340 ext. 4751

Kerr Street and Metcalfe Street

Overview

The reconstruction project will include work on Kerr Street between Wellington Street and Beverly Street, and Metcalfe Street between Blair Road and Park Hill Road. The project includes replacement of watermains, sanitary sewers, and storm sewers. It will also include reconstruction of the asphalt, road base and sub-base, concrete sidewalks, and concrete curb and gutter.

Timeline

Planned construction start date: May 1, 2025

Progress

  • Project is out for tender.

Road Closures

  • Kerr Street and Metcalfe Street will be open to local traffic only.

Notices

Contact Information

Scott MacDonald
Project Engineer
City of Cambridge
(519) 623-1340 ext. 4616

Sanitary Sewer Main CIPP Lining Contract - Citywide

Overview

The City of Cambridge will be proceeding with the rehabilitation of existing sanitary sewer mains on various streets across the City as part of the 2025 Sewer main Rehabilitation program. Sewer mains will be rehabilitated using a Trenchless (“Minimal Dig”) Technology method which will require a minimized amount of excavation. All non-PVC sewer services from the sewer main to property line within working limits will be replaced. (subject to accessibility at the property line) The following locations are included in this year’s rehabilitation program: The rehabilitation of 1550m of Sewer mains sizes ranging from 200mm-375mm Citywide, primarily using cured-in-place-pipe (CIPP) lining and includes potential lining or renewal of estimated 121 sanitary services and other miscellaneous works, for the rehabilitation of defective sewer mains.

1. Hamilton St. (Dover St S. to Church St S.)

2. Westminster Dr S. (Queenston Rd. to Rose St.)

3. 633 Parkview Cres. To 328 Fountain St S.)

4. Argyle St S. (Moore St. to Vine St.)

5. Laneway 155 (Salisbury Ave. to Gladstone Ave.) 

Timeline

Planned construction start date is May 15, 2025

Progress

  • Tender awarded to Aqua Tech Solutions Inc.
  • Contractor will start pre-construction video inspections and cleaning pipes April 7th, 2025 for a period of 3 weeks.

Road Closures

  • No Road closures Expected. There will only be temporary lane closures during pre-construction video inspections, pipe preparation and CIPP lining process. 

Notices

  • Residents affected will be notified. Please see link to notices above. 

Contact Information

Deepak Manoj
Project Engineer
City of Cambridge
(519) 623-1340 ext. 4620

 

Middle Block Road Sanitary Trunk Sewer Construction

Overview

Work includes the construction of approximately 1145m of 1050mm diameter sanitary trunk sewer in Middle Block Road between Intermarket Road and Fountain Street North.

Timeline

Road is scheduled to be closed on January 27, 2025 with construction starting soon afterward. The road is anticipated to be reopened in late July 2025.

Progress

  • Road closure scheduled for January 27, 2025.

Notices

Contact Information

Alex Nichols
Project Engineer
City of Cambridge
(519) 623-1340 ext. 4606

Laneway 200 and Laneway 201 Reconstruction

Overview

The reconstruction project will include work on Laneway 200 (Shaw Avenue West – Fisher Mills Road) and Laneway 201 (Milton Avenue East – Shaw Avenue East). Reconstruction will include the construction of new concrete curb and replacement of asphalt pavement.

Timeline

Planned construction start date: May 5, 2025

Progress

  • Laneway 200 construction work is 0% complete.
  • Laneway 201 construction work is 0% complete.

Road Closures

  • N/A

Notices

Contact Information

Steven Huang
Project Engineer
City of Cambridge
(519) 513-6415

huangs@cambridge.ca

Frequently Asked Questions Re: City Construction Projects

Where can I park and how will access be maintained?
During reconstruction, it will be necessary to close the road to all but local traffic. Access to private property will be maintained as best as possible, but it will be at your own risk as you will be traveling through a construction zone. For times when you do not have access to your property, alternative parking arrangements should be made. Overnight parking will be permitted on adjacent streets, but you will need to abide by all other existing parking restrictions (i.e. don’t block a driveway, don’t park too close to a fire hydrant, don’t park where parking is prohibited, etc.). City staff/representatives will provide more information regarding alternative parking when these situations occur.
Will water service be impacted?

In order to maintain your water service during reconstruction, a temporary above ground watermain will be installed. Temporary service will be connected directly at property line and will still be metered during construction.

Some interruptions to your water service will occur throughout the reconstruction. All planned interruptions should be temporary and occur during normal working hours. You will be notified prior to any planned interruption in order to give you an opportunity to draw sufficient water for personal use until your water is turned back on. You should always keep a small supply of water on hand in case an unscheduled emergency shut down is required.

What are the limits of service upgrades?
Water and sanitary services to individual properties will be upgraded to current standards between the mains and property line during the reconstruction. Any replacement, upgrading or installation of new services on private property between the street line and the building is the responsibility of the property owner. Work on private property requires a plumbing permit application to the City’s building division, for individuals considering private side works. Additional information can be found at: https://www.cambridge.ca/en/build-invest-grow/Permits.aspx
How will my driveway be restored?
When reconstructing the sidewalk or curb, it may be necessary to cut back some driveways to match the new grade. If this is the case, the driveway will be saw-cut, and a patch placed using the same material if possible. Impressed or coloured concrete driveways cannot be replaced to match the original, which is also the case with paving stone driveways (unless the owner has a supply of matching stones that the contractor could use).
What if I have a landscaping or sprinkler system on the City's right of way?

In some locations, shrubs, hedges, and fences may encroach into the City Road allowance which can be an issue when installing new infrastructure. If this is the case adjacent to your property you will be asked to relocate the garden, hedge, etc. onto your property prior to construction taking place.

If you have a sprinkler system installed along the edge of the sidewalk or curb, please remove the piping prior to construction as the contractor and city will not be responsible for damages. You may have it reinstalled after construction is completed if you wish.

How will garbage/blue box/green box collection be maintained?
Blue box, green box and refuse collection will be maintained throughout the duration of construction. When access is restricted by construction operations, the construction crew will place the blue boxes, green boxes and refuse containers at a location accessible by the collection service on collection days. To minimize problems during construction, it would be appreciated if all refuse is bagged – yard waste in paper bags, household garbage in plastic bags. Please ensure that your address is clearly marked on your refuse containers, blue boxes and green boxes.
What if I have special needs?
If someone in your home has physical disabilities or special needs for access to your property, please contact the City’s project manager so that we can minimize the access restrictions where possible.