Contact Us
Project Overview
The City of Cambridge completed a Municipal Class Environmental Assessment (Class EA) to assess various management alternatives for the Riverside Dam to address concerns related to the deteriorating condition of the dam. The study established a long list of management approaches and related alternative solutions and conducted an evaluation of each alternative using appropriate technical, natural, social and economic criteria leading to a short-list of alternatives. Further technical analyses were completed for the short-listed alternatives, including preparation of conceptual designs which considered public and agency input.
A preferred alternative to rebuild the dam was advanced and recommended for implementation. The Project File was completed and the Notice of Study Completion issued. During the Public Review Period the Ministry of Environment, Conservation and Parks (MECP) received five (5) Part II Order Requests. The Ministry completed their review, and the five Requests were denied by the Minister meaning that the City could proceed with implementation of the recommended alternative.
A Consultant was retained by the City to complete the detailed design assignment. Necessary field work and studies were completed, and a design was advanced to the 60% level.
In December 2021 Council received a report from staff that provided an update on the project. The report informed Council that additional funding was required to complete the design and also that the estimated total construction cost had significantly increased from the cost estimate provided at the completion of the Class EA. Council had the option of proceeding with the project by approving the additional funding, or a second option was a passive management approach which included not continuing with the current design project. Council endorsed the passive management approach and not continuing with the design of the new dam.
The passive management approach involves regular inspections of the dam to monitor its condition and assess short-term risks, with any substantive change in condition or risk being promptly reported to Council.
In January 2023 a report from staff was received by Council. The purpose of this report was to provide a summary of the findings from the Riverside Dam inspection completed under the passive management monitoring program in August 2022. At the Council Meeting, the report was sent back to staff with direction to provide an overview presentation on the Riverside Dam at the Budget and Audit Committee meeting in February 2023. At this meeting Council requested that design of the new Riverside Dam be restarted with additional funding to complete the detailed design. The detailed design is now complete, and submissions have been made to approval agencies. The design team will continue to pursue approvals and permits in preparation for construction of the new dam. The new dam construction project is currently in the 10-year capital forecast in 2029.
As part of the passive management monitoring program an inspection was completed in August 2024. The inspection established that the dam remains in poor condition. The dam is in a state in which failure is imminent and is difficult to predict. As such, recommended repairs to the dam should be completed as soon as possible. For the north stop log structure, it was recommended that the raceways be blocked up as was previously done for the south stop log structure, because failure of the stop log structure would compromise the integrity of the dam. The details of this repair are currently being determined through a separate design assignment, and the repair work is planned to be completed in the next year.
Progress to date
Upcoming work
Documents, reports and updates
Progress to Date
- Four public information centres were held during the Class EA.
- Stakeholder Advisory Committee and Technical Advisory Committee meetings took place throughout the Class EA.
- Staff delivered Report 18-103(CD) to Council June 26, 2018 recommending a preferred alternative to rebuild the dam.
- Completed the Project File in July 2018.
- Project File was posted for a 60 day public review period.
- Five (5) Part II Order Requests were received by MECP.
- The Minister of MECP denied the five Part II Order Requests (links to the Minister's letter and the decision table are below) meaning the implementation of the recommended alternative could proceed.
- City completed a Request for Proposal (RFP) process and a Consultant for the implementation phase was retained in February 2020.
- The design assignment was initiated in March 2020.
- Some field work for the design was completed and then the assignment was put on hold by Council direction due to the pandemic.
- Field work and preliminary design was recommenced in September 2020 and is ongoing.
- Options for the new dam were reviewed and a preferred concept was determined. A 30% design has been completed.
- Consultation with agencies and indigenous communities has taken place.
- A virtual public information centre (PIC) is being held from May 17 to May 31 2021.
- The detailed design of the new dam was completed in 2025.
- Approvals and permits are currently being obtained from agencies.
- Design of a repair to the north control structure is underway.
Upcoming Work
- Continue to obtain approvals and permits for the construction of the new dam.
- Complete the design for the repair.
- Complete the repair work.
Study Area
Documents, reports and updates
- Notice of study commencement and public information centre
- Public Information Centre #3 presentation of alternative solutions
- Public Information Centre (PIC) No. 4 for Riverside Dam Class Environmental Assessment
- Public Information Centre #4 presentation of preliminary preferred alternative
- Comment form from Public Information Centre #4
- Stakeholder list
- Final Cultural Heritage Evaluation Report
- 2018 Riverside Dam Inspection Report
- Stakeholder Workshop Report
- Structural Investigation & Review of Repair Feasibility
- Report to General Committee - March 6, 2018
- Report to Council - April 17, 2018
- Notification of Updated Preferred Alternative - April 2018
- Report to Council - June 26, 2018
- Notice of Study Completion
- Riverside Dam Environmental Study Report: Part A, Part B, Part C, Part D
- Letter from the Minister of MECP regarding the Part II Order Requests
- Minister's Decision Table (Minister's Review of Issues Raised by Requestors)
- Council Update Report - December 2, 2021.
- Council Update Report - December 3, 2024
Contact Information
Mr. Scott MacDonald, P. Eng
Project Engineer
City of Cambridge
Development & Infrastructure
50 Dickson Street
Cambridge, ON N1R 5W8
T.: (519) 513-6421
macdonaldscott@cambridge.ca






