The projects listed below are in the pre-construction (or engineering design) phase. View the individual projects for details including proposed construction locations, public meeting date, project engineer and timeline. 

For projects currently under construction, visit our current projects page

Albert Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Albert Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Elliott St - Summit Ave
Albert Street process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2024

Steven Huang

Project documents

No project documents to date.

Argyle Street North

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Argyle Street North. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • King to Duke
Argyle Street North process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 16, 2019

In Progress Awaiting

2023-2024

Walter Buettel

Project documents

Public Information Session Argyle Street, Church Street and Westminister Street

Argyle Street South

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Argyle Street South. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Queenston to King
Argyle Street South process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 16, 2019

In Progress Awaiting

2023-2024

Walter Buettel

Project documents

Public Information Session Argyle Street, Church Street and Westminister Street 

Bechtel Street & Utility Corridor 195

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Bechtel Street and Utility Corridor 195 (South of Bechtel). When reconstruction work occurs it is expected to involve replacing the storm sewer and watermain. Water services will also be replaced to the property line.

Proposed construction locations:

  • Bechtel Street - from Shepherd Avenue to End
  • Utility Corridor 195 - from Bechtel Street - Holiday Inn Drive

Bechtel Street & Utility Corridor 195 process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 10, 2017

In Progress Awaiting

2022-2023

Prasad Samarakoon

Project documents

Public Information Centre - Bechtel Street and Utility Corridor

Bruce Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Bruce. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Ainslie St S to Main St

Bruce Street process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2025

Steven Huang

Project documents

No project documents to date

Byng Avenue

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Byng Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Salisbury Avenue to End

Byng Street process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2024-2025

Matt Holland

Project documents

No project documents to date

Church Street North

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Church Street North. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • King to Duke

Church Street North process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 16, 2019

In Progress Awaiting

2023-2024

Walter Buettel

Project documents

Public Information Session Argyle Street, Church Street and Westminister Street

Church Street South

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Church Street South. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Church St. South: King to Queenston
  • Church St. South: Hamilton to Sherring

Church Street South process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 16, 2019

In Progress Awaiting

2023-2024

Walter Buettel

Project documents

Public Information Session Argyle Street, Church Street and Westminister Street

Clemens Avenue

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Clemens Avenue. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Sheffield to Fisher Mills

Clemens Avenue process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 8, 2019

In Progress Awaiting

2023-2024

Walter Buettel

Project documents

Public Information Session Clemens Avenue

Dayton Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Dayton Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Dayton Street - Water Street North to End

Dayton Street Construction process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

December 2021

Not Complete Awaiting

2025

Scott MacDonald

Project documents

Public Information Centre - Dayton Street - Metcalf Street Construction

Elgin Street North Reconstruction

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Elgin Street North from Glamis Road to the CP Rail Bridge South of Samuelson Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line. 

Proposed construction locations:

  • CP Rail Crossing (South of Samuelson St.) to Glamis Road

Elgin Street North Reconstruction process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

June 20, 2017

In Progress Awaiting

2024-2025

(Two Phases, some Utility Relocation Work 2023)

Steven Huang

Project documents

No project documents to date. 

Gladstone Avenue

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Gladstone Avenue in the locations listed below. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Gladstone Avenue - from Berkley Road to Parkwood Avenue
Gladstone Avenue process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 25, 2017

Complete Awaiting

2022

Scott MacDonald

Project documents

Glendale Place - Ash Street Reconstruction

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Glendale Place and Ash Street in the locations listed below. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Glendale Place - from Sherwood Drive to End
  • Ash Street - from Sherwood Drive to End
Glendale Place - Ash Street Reconstruction process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 25, 2017

Complete Awaiting

2024

Scott MacDonald

Project documents

Groh Avenue

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Groh Avenue. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk and the addition of multi-use trail. Sanitary and water services will also be replaced to the property line.Proposed construction locations

  • Holiday Inn Drive to Bechtel Street
Groh Avenue process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 10, 2017

In Progress Awaiting

2022

Prasad Samarakoon

Project documents

Henry Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Henry Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Elliot St to Ballantyne Ave
Henry Street process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2025

Steven Huang

Project documents

No project documents to date.

Kay Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Kay Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Cedar Street to Victoria Avenue

Kay Street process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2024-2025

Matt Holland

Project documents

No project documents to date

Keffer Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Keffer Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Tannery Street West to Shamrock Street

Keffer Street process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

April 8, 2019

In Progress Awaiting

2023-2024

Walter Buettel

Project documents

Public Information Centre - Keffer Street

Kerr Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Kerr Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Kerr Street - Wellington Street to Beverly Street

Kerr Street Construction process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Completed

December 2021

Not Complete Awaiting

2025

Scott MacDonald

Project documents

Public Information Centre - Roseview Avenue - Kerr Street Construction

Maple Ridge Road

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Maple Ridge Road. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Wellington Street South to Harris Street

Maple Ridge Road process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2024-2025

Matt Holland

Project documents

No project documents to date

McAuslan Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of McAuslan Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • McAuslan St: Albert St to Henry St

McAuslan Street process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2025

Steven Huang

Project documents

No project documents to date.

Metcalf Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Metcalfe Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Metcalfe Street - Blair Road to Park Hill Road West

Metcalfe Street Construction process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

December 2021

Not Complete Awaiting

2025

Scott MacDonald

Project documents

Public Information Centre - Dayton Street - Metcalfe Street Construction

Moore Street - Hamilton Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Moore Street and Hamilton Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Moore Street - Lowther Street South to Dolph Street South
  • Hamilton Street - Lowther Street South to Dolph Street South

Moore Street - Hamilton Street Construction process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

December 2021

Not Complete Awaiting

2025

Scott MacDonald

Project documents

Public Information Centre - Moore Street - Hamilton Street Construction

Oxford Street - Brook Street Construction

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Oxford Street and Brook Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Oxford Street – Roseview Avenue to Laneway 180
  • Brook Street – Wellington Street to Cambridge Street

Oxford Street - Brooke Street Construction process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

June 27, 2018

Complete Awaiting

2024

Scott MacDonald

Project documents

Public Information Centre - Oxford Street - Roseview Avenue - Brook Street Construction

Ramore Street - Gilholm Avenue

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Ramore Street and Gilholm Avenue. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Ramore Street - Gilholm Avenue to Cedar Street
  • Gilholm Avenue - Ramore Street to St. Andrews Street

Ramore Street - Gilholm Avenue Construction process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

December 2021

Not Complete Awaiting

2025

Scott MacDonald

Project documents

Public Information Centre - Ramore Street - Gilholm Avenue Construction

Roseview Avenue

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Roseview Avenue. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Roseview Avenue - Wellington Street to Oxford Street
Roseview Avenue Process Overview
Preliminary DesignPublic Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete June 27, 2018 and December 2021 Not Complete Awaiting 2023 Scott MacDonald

*The section of Roseview Ave between Cambridge Street and Oxford Street was previously designed and the section between Wellington Street and Cambridge Street is currently being designed.

Project Documents

Richardson Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Richardson Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Cedar Street to Victoria Street

Richardson Street process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2024-2025

Matt Holland

Project documents

No project documents to date

Serviss Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Serviss Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Albert St to Henry St
Serviss Street process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2025

Steven Huang

Project documents

No project documents to date.

Spruce Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Spruce Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Bruce St to Main St

Spruce Street process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2025

Steven Huang

Project documents

No project documents to date.

Wellington Street

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Wellington Street. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations:

  • Wellington Street – Beverly Street to Dundas Street North

Wellington Street process overview
Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
Complete

June 27, 2018

Complete Awaiting

2026

Scott MacDonald

Project documents

Public Information Package Brook Street, Cambridge Street, Park Hill Road East, Oxford Street, Roseview Avenue and Wellington Street Reconstruction.

Wellington Street South

The City of Cambridge has undertaken engineering work to prepare for the reconstruction of Wellingston Street South. When reconstruction work occurs it is expected to involve replacing the sanitary sewer, storm sewer, watermain, curb and gutter, road and sidewalk. Sanitary and water services will also be replaced to the property line.

Proposed construction locations

  • Bruce Street to Walnut Street

Wellington Street South process overview

Preliminary DesignPublic  Information CentreDetailed DesignBudget ApprovalExpected ConstructionProject Engineer
In Progress

To be scheduled

Awaiting Awaiting

2024-2025

Matt Holland

Project documents

No project documents to date