In addition to City-led projects underway across Cambridge, there are numerous projects being completed by private developers. Below is a listing of the major developments currently under construction, copies of public notices and contact details.

For more information, contact engineering@cambridge.ca

Cambridge West Community

Overview

Cambridge West Community is roughly a 90 ha area composed of four residential subdivisions: Hallman Subdivision, Cachet Subdivision, Newman Subdivision and Grand Ridge Estates Subdivision. Hallman, Cachet and Huron Creek subdivisions are generally located west of Devil’s Creek, north of Blenheim Road, south of Westcliff Way and east of the City’s municipal boundary, while Grand Ridge Estates is bounded by Blenheim Road to the north and the Canadian Pacific Railway to the south. Hallman and Cachet are collectively referred to as Westwood Village and Huron Creek as Westwood Village Preserve. 

Grading, municipal servicing and road construction works, including the realignment of Blenheim Road from Devil’s Creek to the City’s municipal boundary, have commenced and will continue through 2023 for Hallman, Cachet and Huron Creek, while Grand Ridge Estates is in the draft plan stage.

Construction of Bismark Park is underway and will continue through 2023. This new community park is being built by Hallman Construction Ltd. and donated to the City of Cambridge. The park will provide numerous recreation opportunities for residents and includes a splash pad, skatepark, washrooms, playgrounds, a multi- sport court, trails and picnic areas. 

Documents

Greengate Village Subdivision – Phase 6 

Overview

Phase 6 of this subdivision is the completion of the final 37 lots at north end of the Greengate Village Subdivision. This phase of development will include the extension of Nottinghill Drive to Main Street. Grading, municipal servicing, and road construction works have been completed.  Home construction will continue through 2024.

Documents

Moffat Creek Subdivision

Overview

A 49-hectare residential subdivision located in the northern of the South-East Galt Community near the intersection of Wesley Boulevard and Maple Bush Drive. Municipal servicing and road construction works commenced in October 2023 and will continue through 2024.

Documents

Morrison Creek Estates Subdivision 

Overview

Morrison Creek Estates is a 31-hectare residential subdivision located north of Dundas Street S., east of Vanier Drive and South of Ripplewood Road. Construction of municipal service extensions on Dundas Street S. from Branchton Road to Vanier Drive and the Sanitary Pumping Station located within subdivision commenced in 2022. Home construction will continue through 2024.

Documents

Pinebush Subdivision 

Overview 

The Pinebush Subdivision is a 15-hectare residential subdivision located north of Pinebush Road, west of Struck Court and south of Highway 401. The two new municipal roads with the subdivision have been constructed. The next phase of construction will include the condominium blocks and street-fronting townhouses.

Documents

Saginaw Subdivision – Stage 1 and Stage 2 

Overview

The Saginaw subdivision is a 26-hectare residential subdivision located on the former Saginaw Golf Course Lands in the general are of Essex Point Drive, Green Vista Drive, Burnett Avenue and Saginaw Parkway. 

Stage 1

Encompasses the 17-hectare paces of land located west of Essex Point Drive. Grading, municipal servicing, and road construction commenced in 2023. Home construction through 2024.  

Stage 2

Encompasses the 9-hectare parcel of land located east of Essex Point Drive. Municipal servicing, and road construction works have been completed in this Stage. Freehold home construction was completed in 2024. Home construction within the central condominium blocks will commence once site plan approval and building permits are obtained on these blocks

SouthPoint Subdivision

Overview

SouthPoint is a 29-hectare residential subdivision located south-east of the intersection of Wesley Boulevard and Fitzgerald Drive and north of the intersection of Dundas Street S. and Branchton Road. The subdivision was formerly referenced as the Bosdale Subdivision. The balance of the grading, municipal servicing, and road construction have been completed. Home construction will continue through 2024.

Documents

iPort Industrial Subdivision

Overview

A 109-hectare industrial subdivision located in north Cambridge between Allendale Road and Middle Block Road and between Riverbank Drive and Fountain Street.  Grading commenced in Fall 2022 and municipal servicing and road construction works commencing mid-2023.

Documents

 

Highland Ridge Subdivision

Overview

Park works (regrading, seeding, and watering) at Lynn Freure Park are now completed. The park was opened on August 4, 2023. 

 