In addition to City-led projects underway across Cambridge, there are numerous projects being completed by private developers. Below is a listing of the major developments currently under construction, copies of public notices and contact details.

For more information, contact engineering@cambridge.ca

Cambridge West Community

Overview

Cambridge West Community is roughly a 90 ha area composed of four residential subdivisions: Hallman Subdivision, Cachet Subdivision, Newman Subdivision and Grand Ridge Estates Subdivision.  Hallman, Cachet and Huron Creek subdivisions are generally located west of Devil’s Creek, north of Blenheim Road, south of Westcliff Way and east of the City’s municipal boundary, while Grand Ridge Estates is bounded by Blenheim Road to the north and the Canadian Pacific Railway to the south.  Hallman and Cachet are collectively referred to as Westwood Village and Huron Creek as Westwood Village Preserve. 

Grading, municipal servicing and road construction works, including the realignment of Blenheim Road from Devil’s Creek to the City’s municipal boundary, have commenced and will continue through 2021 for Hallman, Cachet and Huron Creek, while Grand Ridge Estates is in the draft plan stage.

Documents

Greengate Village Subdivision – Phase 6 

Overview

Phase 6 of this subdivision is the completion of the final 37 lots at north end of the Greengate Village Subdivision. This phase of development will include the extension of Nottinghill Drive to Main Street. Grading, municipal servicing, and road construction works have been completed.  Home construction will continue through 2023.

Documents

Moffat Creek Subdivision

Overview

A 49-hectare residential subdivision located in the northern of the South-East Galt Community near the intersection of Wesley Boulevard and Maple Bush Drive. Grading is commenced in Summer 2022 with municipal servicing and road construction works commencing in late 2022/early 2023.

Documents

Morrison Creek Estates Subdivision 

Overview

Morrison Creek Estates is a 31-hectare residential subdivision located north of Dundas Street S., east of Vanier Drive and South of Ripplewood Road. Construction of municipal service extensions on Dundas Street S. from Branchton Road to Vanier Drive and the Sanitary Pumping Station located within subdivision commenced in 2022. Home construction to commence in 2023. 

Documents

Pinebush Subdivision 

Overview 

The Pinebush Subdivision is a 15-hectare residential subdivision located north of Pinebush Road, west of Struck Court and south of Highway 401. The two new municipal roads with the subdivision have been constructed. The next phase of construction will include the condominium blocks and street-fronting townhouses.

Documents

Saginaw Subdivision – Stage 1 and Stage 2 

Overview

The Saginaw subdivision is a 26-hectare residential subdivision located on the former Saginaw Golf Course Lands in the general are of Essex Point Drive, Green Vista Drive, Burnett Avenue and Saginaw Parkway. 

Stage 1

Encompasses the 17-hectare paces of land located west of Essex Point Drive. Grading, municipal servicing, and road construction to continue through 2023. 

Stage 2

Encompasses the 9-hectare parcel of land located east of Essex Point Drive. Municipal servicing, and road construction works have been completed in this Stage. Home construction will continue through 2023.

Documents

SouthPoint Subdivision

Overview

SouthPoint is a 29-hectare residential subdivision located south-east of the intersection of Wesley Boulevard and Fitzgerald Drive and north of the intersection of Dundas Street S. and Branchton Road. The subdivision was formerly referenced as the Bosdale Subdivision. Grading, municipal servicing, and road construction have been completed.  and will continue through to the end of 2022. Home construction will continue through 2023.

Documents

iPort Industrial Subdivision

Overview

A 109-hectare industrial subdivision located in north Cambridge between Allendale Road and Middle Block Road and between Riverbank Drive and Fountain Street.  Grading commenced in Fall 2022 and municipal servicing and road construction works commencing mid-2023.

Documents

 

Highland Ridge Subdivision

Overview

Please be aware that there will be park works (regrading, seeding and watering) being undertaken at Lynn Freure Park commencing tentatively May 24th, 2023, weather dependent. The work will be ongoing for the duration of approximately 4 weeks. The park will be completely closed for about 2 weeks to accommodate the regrading works. The seeded areas will remain closed to public use for approximately an additional 2 weeks, to allow for proper germination. Seeded areas will be available for public use once grass growth is established and all construction fencing is removed.

 

Should you have any questions please reach out to:

Joe Moon
Meritech Engineering
Tel: 519 623 1140

Jennifer Hachler
GSP Group Inc
Tel: 226 243 7328

Daryl George
Grand Ridge Estates
Tel: 519 578 7771