Project Overview

The City of Cambridge completed an Environmental Assessment (EA) Study for a transportation assessment of Beverly Street between Dundas Street North and Elgin Street North. The approved improvements accommodate all road users and meets the community design objectives. The project is in the stage of detailed design and approvals.

Progress to Date

  • EA Project File Final Report Completed
  • EA Project File Closed
  • 30% Detail Design Submission Received

Upcoming Work

  • 60% Detail Design Submission
  • Canadian Pacific Railway Design Review/Approvals

Study Area

 Study area diagram highlighting Beverly St from Dundas St to Samuelson St

Documents, reports and updates 

Contact Information

Prasad Samarakoon, P.Eng
Project Engineer
City of Cambridge
T.: (519) 623-1340 Ext. 4539
samarakoonp@cambridge.ca

Steve Taylor, P.Eng.
EA Project Manager
BT Engineering
T.: (519) 672-2222
stevenj.taylor@bteng.ca